Elevated helideck construction covers the steel support structure, deck plating in steel or aluminium, connections, foundations, perimeter safety netting and access stairs. Design uses helicopter loads, with wind and seismic per SBC 301 and deck geometry per ICAO Annex 14 Volume II. Fabrication follows AISC 360 and AWS D1.1, with mill certificates, weld and NDT records at handover.
An elevated helideck is a landing platform carried on a steel structure above ground, above a building or beside a plant. It is chosen where a ground-level pad does not fit the site, or where the helicopter must land at the level of the facility it serves. NLS Contractors prices it as a works package: foundations, steel supply, fabrication, protection, erection, decking, safety netting, stairs and handover documents.
The design basis starts with the helicopter. Design loads for landing and for the parked aircraft come from the design helicopter the owner names, and wind and seismic actions are taken from SBC 301. Deck geometry follows ICAO Annex 14 Volume II, and CAP 437 where the specification cites it. The deck itself is plated in steel or in aluminium, depending on the specification, with a non-slip finish, drainage and a perimeter safety net.
Fabrication follows recognised steel codes. AISC 360 governs the member and connection design, and AWS D1.1 governs welding, with welder and procedure qualifications on record. Corrosion protection is a major cost line and a durability point: ISO 12944 paint systems are chosen by corrosivity category, and coastal sites such as Jeddah, Dammam and Khobar push the category up, or the specification calls for hot-dip galvanising to ISO 1461. Steel sections and plate can be sourced through NLS Industries (nlsindustries.com) and priced in the same offer.
Foundations carry the loads into the ground, whether as pad footings, piles or a connection into an existing structure. Erection is crane work, and the offer states the crane and access assumptions because they drive the programme. Access stairs, handrails and the safety net follow the drawings.
The lighting, power and firefighting provisions of the deck are covered by their own works packages, and aviation lighting supply sits with Northlane Solutions. GACA approval belongs to the owner through the consultant, and this package supplies the construction documents behind it.
Handover includes shop drawings, mill certificates, weld and NDT records, coating records and as-built drawings. To price an elevated helideck, send the IFC structural drawings, the heliport specification clauses, the design helicopter and the BOQ. Price and lead time depend on tonnage, protection system and site access, and the offer states both.
Specifications
- ✓Steel support structure, connections and foundations; deck plating in steel or aluminium
- ✓Design loads from the owner's design helicopter; wind and seismic per SBC 301
- ✓Deck geometry per ICAO Annex 14 Volume II, and CAP 437 where the specification cites it
- ✓Fabrication to AISC 360 and AWS D1.1; protection by ISO 12944 paint systems or hot-dip galvanising to ISO 1461
- ✓Perimeter safety netting and access stairs
- ✓Handover: shop drawings, mill certificates, weld and NDT records, coating records, as-builts
Frequently Asked Questions
When is an elevated helideck chosen over a ground-level pad?+
When site levels, obstacles or the facility layout rule out a ground pad, or when the helicopter must land at the level of the building or plant it serves. The owner and the consultant make that choice.
Steel or aluminium deck plating: which is used?+
Whichever the specification names. Steel is common for onshore decks; aluminium is lighter and resists corrosion. The offer prices the specified material and notes the supporting structure it implies.
How does a coastal site change the steel protection?+
Salt air raises the ISO 12944 corrosivity category, which means a thicker or more layered paint system, or hot-dip galvanising. The category is set in the specification and the offer prices the system it names.
What fabrication records are handed over?+
Mill certificates for the steel, weld maps and NDT records, coating thickness records and as-built drawings, so the consultant can confirm the deck matches the approved design.
Who supplies Elevated Helidecks (Steel Structure) in Saudi Arabia?+
NLS Contractors (Northlane Solutions Company) supplies Elevated Helidecks (Steel Structure) across Saudi Arabia, including Riyadh, Jeddah, Dammam and Jubail. Send your specification and quantities to info@nlscontractors.com or info@northlanesolution.com for a quotation.
Related products

Helipad Electrical & Lighting Installation
Helipad electrical and lighting installation covers perimeter lights, floodlights, FATO and approach lights, the lit wind direction indicator, obstruction lights, power supply, control panel and backup. Installed to ICAO Annex 14 Volume II visual aids, GACAR Part 138 and FAA AC 150/5390-2C, with IEC 62305 earthing where specified. Handover includes circuit test records, function tests, as-builts and O&M manuals.

Helipad Drainage & Firefighting Provisions
Helipad drainage and firefighting provisions cover surface drainage with fuel containment, hose reels, extinguishers, hydrants or foam provisions, and rescue equipment storage. The provision level is set by the owner and Civil Defense, with NFPA 418 and ICAO Annex 14 Volume II guidance, in Riyadh, Jeddah, Dammam and Khobar. Handover includes drainage and fire drawings, pressure test records and as-builts.

GACA Approval Support for Helipad Construction
GACA approval support for helipad construction assembles the construction-side documents behind the owner's GACAR Part 138 submission: drawings, obstacle surface inputs, lighting and marking datasheets, inspection records and as-builts. Approval belongs to the owner through the consultant. Delivered as one indexed document set for projects in Riyadh, Jeddah, Dammam and Khobar.

Ground-Level Helipad Construction
Ground-level helipad construction covers the FATO, TLOF and safety area, a bearing pavement in reinforced concrete or asphalt, shoulders, drainage, perimeter fence and access. Geometry follows GACAR Part 138, ICAO Annex 14 Volume II and FAA AC 150/5390-2C for the owner's design helicopter, anywhere in the Kingdom, with drawings, test records and a handover pack for the GACA submission.

Hospital Rooftop Helipads
Hospital rooftop helipad construction covers the structural interface to the roof slab or frame, the TLOF surface, safety net, access route to the emergency department, lighting and firefighting provisions. Built to GACAR Part 138, ICAO Annex 14 Volume II, NFPA 418 and Civil Defense requirements in Riyadh, Jeddah, Dammam and Khobar, with load path documentation and a handover pack.